Road Resurfacing Work Schedule
Week of August 18-29, 2025 (Updated)
Friday August 22, 2025
• Road work on Soule Rd from Main St to Meadow View Rd
• Road work on Delmor Ave from Main St to the end
Soule Rd Detour – Main St to Oakland St to Meadow View Rd
Delmor Ave Detour – Delmor Cir and Decorie Dr
Wednesday August 27
• Paving Soule Road detour as above
Thursday August 28
• Paving Delmor Ave detour as above