Paving Update, 7/29
Rain continues to cause delays in the road work schedule.
Monday
Road work will continue on Stony Hill Rd. Milling on Three Rivers from Chilson Rd to north of Circle Dr. Milling on Main Street from Woodland Dell to Brookmont. Sidewalk construction on Main St.
Tuesday
Road work will continue on Stony Hill Rd. Milling on Main Street from Woodland Dell to Brookmont.
Wednesday (If there is no rain)
Paving on Stony Hill Rd between Briar Cliff Drive and Sunnyside Terrace. Please use alternate routes as the road will be closed to thru traffic. Expect major delays and detours.