Paving Schedule for Week of August 19-23, 2024
Work will take place on the following roads (weather permitting);
08/19—Sidewalk Excavation to start on Main St between Tinkham Rd. & Soule Rd.
Expected date of completion 08/23
08/19 – Maiden Ln.-Berm
Red Gap Rd., Valley View Dr. and Stirrup Ln.-Paving
08/20 –Inwood Dr. and Westwood Dr. –Paving
08/21—Echo Hill Rd. – Paving
Burleigh Rd. -Leveling, Shims and Berm Pad
08/22—Burleigh Rd.—Berm and O/L Powers Dr. to Main St.
08/23—TBD